Welcome to the Broadway Construction Page!
Project Name: Broadway Sidewalks (CIP #41606) and Broadway Maintenance (CIP #42003)
Project Limits: Broadway from Main Street/Mosquito Road to Schnell School Road
Project Work: New sidewalks, underground utility work (sewer, storm drain, and water system), and pavement rehabilitation
Project Contractor: Doug Veerkamp General Engineering, Inc.
Project Start Date: March 18, 2024
Project End Date: End of November 2024
Dion Carr, Resident Engineer, Dewberry Engineers, dcarr@dewberry.com, (916) 276-4721
Project Updates:
October 19, 2024: Weekly Update 30
October 12, 2024: Weekly Update 29
October 7, 2024: Weekly Update 28
September 2, 2024: Weekly Update 23 September 9, 2024: Weekly Update 24 September 14, 2024: Weekly Update 25 September 20, 2024: Weekly Update 26 September 30, 2024: Weekly Update 27
August 2, 2024: Weekly Update 19 August 9, 2024: Weekly Update 20 August 17, 2024: Weekly Update 21 August 24, 2024: Weekly Update 22
July 1, 2024: Weekly Update 14 July 8, 2024: Weekly Update 15 July 15, 2024: Weekly Update 16 July 22, 2024: Weekly Update 17 July 29, 2024: Weekly Update 18
June 3, 2024: Weekly Update 10 Broadway Night Work Exhibit June 10, 2024: Weekly Update 11 June 17, 2024: Weekly Update 12 June 24, 2024: Weekly Update 13
May 3, 2024: Weekly Update 6 May 10, 2024: Weekly Update 7 May 17, 2024: Weekly Update 8 May 28, 2024: Weekly Update 9
April 9, 2024: Weekly Update 3 April 19, 2024: Weekly Update 4 April 26, 2024: Weekly Update 5
March 29, 2024: Project construction began on Wednesday, March 20th! During the first few weeks, the contractor is potholing to confirm utilities. In the second week of April, the contractor will begin the underground utility work starting at Mosquito Road. Please pay close attention to traffic control as the work location moves during potholing, and reduce speeds in the work zones. Thank you!